Building Your Dream Home-- Part 3

Exterior Framing Continues

With the homes sub-floor down and the outside walls framed and up, the framing team was on to the roofing system. Though the roof was rather basic in structure with simply a 12/12 pitch and no valleys it was a substantial framing undertaking due to just the size and height of it. The house was 32 feet wide by 44 feet in length, and the outside side walls stood 11 feet high in the fantastic space. This exterior wall height of 11 feet equated into a roofing ridge that was 27 feet off the flooring of the excellent room. Consequently staging was needed to set up the ridge pole and roofing system rafters. In addition, because the period from the top of the walls to the ridge was so long, heavy 2x12s were required for the roofing system rafters. Within best plumber in Canberra a week, nevertheless, the group had actually finished the installation of the roofing system rafters and your house began to handle genuine shape.

I ought to comment briefly about the sub-floor and exterior walls before I move on.

I selected using tongue and groove plywood for the sub-flooring rather than OSB/particle board as I was concerned that the OSB was too conscious moisture. I was concerned about this, both from the building and construction phase and from typical home usage. I was worried that throughout the building and construction phase that snow and ice might possibly cause harm such as warping. I have seen this before when OSB was utilized on sub-flooring. I was also worried that during the life of the home, that there could be water events, e.g. a dripping dishwashing machine or washer device that likewise could also cause water damage to the floor. I also believe that plywood is stronger and that it would offer a more solid and rigid floor.

Regarding the exterior wall framing I utilized 2 × 6 building. This is normal in New England as the extra wall depth enables higher insulation elements; a need to in colder climates.

Sheathing the Beyond the Home

In order to get pipes and electric contractors onto a website normally they desire the home buttoned up. This includes the roofing system shingled and the doors and windows on. Hence my framing team moved onto the outside sheathing once the walls and roofing system framing were complete.

As with the sub-floor, I again chose plywood for the exterior sheathing for the very same reasons pointed out earlier. On the outside walls outside grade plywood was utilized. On the roofing 5/8 outside grade plywood was used. I understand many contractors today utilize OSB for both the walls and roof, however, I still think for stronger construction plywood is the way to go.

The sheathing effort took about a week to finish. Throughout this time outside doors and windows showed up on the site. Staging the delivery of product lowers theft and insurance threat in addition to keeps a less messy building and construction site. However, as I have shown previously, interaction is important when you are doing Just-in-Time material delivery.

Installing Outside Doors and Windows

The installation of the doors and windows was a major endeavor for this task as the lake side view of the home was literally a wall of windows; 32 feet in width and 27 feet in height. A great deal of engineering had actually entered into the window design so that the 10 big customized windows would mesh like a jig saw puzzle. This stated, when the windows arrived on site and were inspected, it was figured out that a few of them were not developed correctly to the dimensions defined. After much argument with the framing team, the window vendor and me we reached a compromise on sharing the cost of repairing the windows. The window supplier reclaimed the poorly sized windows and the framing crew started the setup of the doors and what windows they might set up. Luckily the window vendor had the ability to return to the site with the properly sized windows within a few days and the building and construction stage did not miss a beat.

Completing the Interior Framing

With the doors and windows set up, the framing team proceeded to finish the Interior Framing. This was an exciting time, as the rooms began to take genuine shape. You might now stroll down hallways and into bed rooms and closet areas. Within just a couple of days the interior walls were total and the framing team continued onto the roof for the shingling.

I should note that 2 × 4 building was utilized on the interior walls as insulation was not needed on the interior walls.

Shingling the Roof

The last task to finish before the house could be categorized as Buttoned Up was to install the shingles on the roofing. Fortunately my framing team was also able to do this task, therefore removing the need for yet another subcontractor.

I selected a thirty years architectural shingle due to the quality and look I was trying to attain on the home.

Though relatively a simple roofing, it was rather large and the weather was less than hospitable. Subsequently it took nearly 2 weeks to finish this task. Nevertheless, with the roof complete, my electrical and pipes specialists were now able to begin their work.

Also, with the primary home now structurally total, the framing team moved onto the garage framing and construction phase. As a result of staging the garage behind the primary home construction stage, I had the ability to have subcontractors work in parallel without getting in each others way.

Rough Electric and Plumbing

With the house Buttoned-Up, my Electric and Plumber subcontractors showed up to start the roughing in stage of their particular tasks.

Rough Electric

I had actually met a few days before on site with the Electric subcontractor to discuss the placement of all the wall outlets and switches, as well as where the light fixtures would be positioned. Throughout our conversation he marked the wall studs for the placements of the electrical electrical wiring boxes so that we could picture the entire electric electrical wiring scheme. We also marked where the telephone and cable television boxes would reside.

During the electrical rough in electrical wiring stage, the electrical contractor set up all the electrical wiring boxes and ran wire from the boxes to where the main circuit panel box would reside.

Rough Plumbing

As with the Electrical Subcontractor, I had fulfilled a number of weeks earlier with the Plumbing Professional. Throughout this conference we discussed the kind of heat for the home, in addition to where the restrooms and cooking area were to live in the home. We likewise discussed kinds of restroom components including tubs, sinks and toilets. As a result, when he showed up on site he new exactly where to run main drain and supply pipes and vent stacks. He also roughed in all of the plumbing for each bathroom and kitchen area pipes fixture.

image

Within a week both the Electrical and Rough Plumbing specialists had finished their tasks and had actually successfully passed their respective examinations.